In marine and industrial operations, equipment downtime can quickly affect productivity, schedules, and operating costs. When a client required an urgent replacement for a DESMI NSL100-215/A02 Vertical Centrifugal Pump, AKT responded with a fast-track sourcing and delivery solution designed to keep operations moving.
Although the standard OEM lead time was approximately 3–4 months, AKT successfully supplied the complete pump within 25 working days. This rapid turnaround helped the client avoid extended downtime and maintain continuity in a critical marine application.
Project Requirement
The client required an urgent replacement pump for a marine operation in Africa, where delays could have resulted in vessel or plant downtime. The key requirement was to source a reliable OEM-grade DESMI pump and deliver it within a significantly shorter timeline than the standard manufacturer lead time.
Equipment Supplied
AKT supplied a DESMI vertical centrifugal pump matching the client’s technical and operational requirements.
Technical Details
• Equipment: Vertical Centrifugal Pump
• Model: NSL100-215/A02
• Type: 672736
• Capacity: 90 m³/h
• Working Pressure: 0.4 MPa / 4.01 bar
• Speed: 2930 RPM
• Power: 18.5 / 22.2 kW
The main challenge was time. With a typical OEM delivery period of 3–4 months, the client needed a faster solution to prevent operational disruption. Any delay could have increased downtime risk, affected schedules, and resulted in additional cost exposure.
• Standard OEM lead time of 3–4 months
• Urgent requirement for a marine pump replacement in Africa
• Risk of downtime and operational delay
• Need for reliable OEM-grade sourcing
• Pressure to reduce procurement lead time without compromising quality
AKT’s Fast-Track Supply Solution
AKT leveraged its sourcing network, technical understanding, and procurement experience to identify and supply the required DESMI pump within an accelerated timeline. By coordinating closely with suppliers and prioritizing the client’s urgent requirement, AKT reduced the delivery period from several months to just 25 working days.
Results Delivered
• Delivered the DESMI NSL100-215/A02 pump within 25 working days
• Reduced the expected lead time from 3–4 months to under one month
• Helped prevent extended marine operational downtime
• Supported continuity for a critical vessel or plant application
• Reduced the client’s exposure to delay-related costs
Why Clients Choose AKT
AKT supports marine, oil and gas, and industrial clients with responsive procurement solutions for critical equipment and spare parts. From emergency breakdown support to OEM and equivalent sourcing, AKT focuses on delivering the right parts quickly, reliably, and cost-effectively.
AKT continues to support the marine, oil & gas, and industrial sectors with:
• Marine centrifugal pumps and related equipment
• Marine engine spare parts and industrial components
• Emergency breakdown and urgent procurement support
• OEM and equivalent sourcing for global brands
• Marine and industrial procurement solutions across the UAE, Middle East, and Africa